Congleton Hydro Newsletter November

Congleton Hydro Newsletter November

A Major Milestone The Volts and Amps are Flowing!   Since the last newsletter, Congleton Hydro has been in continuous generation (apart from a few short shutdowns to facilitate safe working on cladding etc). From about mid-September we have now exported 30MWhrs...
Congleton Hydro Newsletter November

Congleton Hydro October Newsletter

Full Power – Fully Operational – Unattended Operation After almost six years since the first meeting over a few pints to discuss the concept of a Community Hydro using the power generated by Havannah Weir, Congleton Hydro has been operational for the last...
Congleton Hydro Newsletter November

Congleton Hydro Newsletter September

The Holy Trinity  Archie, you know all about, he even has his own world-wide fan club!!, The G99 Protection Relay was the focus of the August Newsletter—crucially important to allow us to connect to the external world i.e. The Grid! All good stuff but we need the...
Congleton Hydro Newsletter November

Congleton Hydro Newsletter August

We have G99 Lift Off!!!! So what? we hear you say, big deal—what has a soft ice cream with a flake, or a multi-nation economic jamboree got to do with our Hydro? Well, it is one of the most important of the approvals we need to obtain, (seems our whole lives have been...
Congleton Hydro Newsletter November

Congleton Hydro Newsletter July 2021

Archie Goes Electric. Finally, Archie briefly wakes up and helps demonstrate that power can be generated from Congleton Hydro.  After rucks of testing, sensor calibrating, parameter tweaking and more testing, it was time to feed his insatiable appetite and give him a...