by HydroCat | May 5, 2021 | Newsletters
Breakthrough!!!! To the open waters and beyond! Welcome to the latest (May 2021) Congleton Hydro Newsletter. After the euphoria of getting Archie successfully installed into his new home, it has been back to the grind, focussing on the completion of the site...
by HydroCat | Feb 3, 2021 | Newsletters
Rain and More Rain!!! We should not be surprised, as, after all, it is mid-winter, but the first few weeks of January have seen some atrocious weather but also some good periods. As mentioned in a previous newsletter the River Dane is a high spate river, being...
by HydroCat | Jan 5, 2021 | Newsletters
Happy New Year and Welcome to 2021 Many people would say that 2020 has been a most terrible year and wish it had just been a bad dream. I guess that on a personal note, the members of Congleton Hydro would agree but from a Project viewpoint, 2020 has been a great year...
by HydroCat | Dec 2, 2020 | Newsletters
Archie the Screw has arrived, but we are almost screwed by the Georgians!!!November has seen a major milestone with the delivery of the Archimedes Screw but also November produced some unforeseen ground conditions that have set us back by a few weeks.After a long...
by HydroCat | Nov 4, 2020 | Newsletters
Clocks Back but Hydro Progress is Forwards!Despite the grotty weather during the period of October, progress made by our site civils contractor CT Construction Ltd has been quite positive although inevitably some slippage has occurred.With the cofferdam in place...