Congleton Hydro Newsletter June 2021

Congleton Hydro Newsletter June 2021

Wot! the Access Track has disappeared. Access Track filled in with “spoil” from construction.Now we cannot go backwards—only forwards!!  However, before the slippery downhill slope started its return to nature and the access track across the field was returned to its...
Congleton Hydro Newsletter June 2021

Congleton Hydro Newsletter September

August was one step forward but the other step going nowhere. The cable installation started as planned and is proceeding to schedule with the first 500m laid between the hydro site at Havannah and Eaton Bank Academy. The second 500m is currently in the process of...