by HydroCat | Oct 12, 2020 | Newsletters
Hallelujah!!!!September has been the start of the realisation of the dream. During the past 4-5 years it sometimes seemed like Mission Impossible, well it is now Mission Happening. We have an access trackway from the main road and perhaps to the greatest relief of...
by HydroCat | Sep 4, 2020 | Newsletters
August was one step forward but the other step going nowhere. The cable installation started as planned and is proceeding to schedule with the first 500m laid between the hydro site at Havannah and Eaton Bank Academy. The second 500m is currently in the process of... by HydroCat | Jul 4, 2020 | Newsletters
With all the funding in place and the Hydro generation Scheme on course to be a reality (not just a dream!!), this is the first of a series of newsletters to keep you updated on key aspects of the project and progress towards generating the all-important Volts and...
by HydroCat | May 5, 2020 | Newsletters
At long last, after four years of planning, designing, calculating, learning, rucks of hard work, despair and euphoria, progressing one step at a time and sometimes backwards Congleton Hydro is set to become a reality. The Community Share Offer closed at midnight on... by HydroCat | Mar 4, 2020 | Project Updates
Last Sunday we had Bob and Paul explaining the key details about Congleton Hydro scheme. Enjoy the...