by HydroCat | Dec 2, 2020 | Newsletters
Archie the Screw has arrived, but we are almost screwed by the Georgians!!!November has seen a major milestone with the delivery of the Archimedes Screw but also November produced some unforeseen ground conditions that have set us back by a few weeks.After a long...
by HydroCat | Nov 4, 2020 | Newsletters
Clocks Back but Hydro Progress is Forwards!Despite the grotty weather during the period of October, progress made by our site civils contractor CT Construction Ltd has been quite positive although inevitably some slippage has occurred.With the cofferdam in place...
by HydroCat | Oct 12, 2020 | Newsletters
Hallelujah!!!!September has been the start of the realisation of the dream. During the past 4-5 years it sometimes seemed like Mission Impossible, well it is now Mission Happening. We have an access trackway from the main road and perhaps to the greatest relief of...
by HydroCat | Sep 4, 2020 | Newsletters
August was one step forward but the other step going nowhere. The cable installation started as planned and is proceeding to schedule with the first 500m laid between the hydro site at Havannah and Eaton Bank Academy. The second 500m is currently in the process of...
by HydroCat | Aug 3, 2020 | Newsletters
July has been a month of hope and anticipation for the Hydro team. In last month’s newsletter, we mentioned that whilst all plans were focused on-site work physically starting during the week of August 3rd, there were two precursor activities outside of our control... by HydroCat | Jul 4, 2020 | Newsletters
With all the funding in place and the Hydro generation Scheme on course to be a reality (not just a dream!!), this is the first of a series of newsletters to keep you updated on key aspects of the project and progress towards generating the all-important Volts and...