by HydroCat | Nov 4, 2020 | Newsletters
Clocks Back but Hydro Progress is Forwards!Despite the grotty weather during the period of October, progress made by our site civils contractor CT Construction Ltd has been quite positive although inevitably some slippage has occurred.With the cofferdam in place...
by HydroCat | Aug 3, 2020 | Newsletters
July has been a month of hope and anticipation for the Hydro team. In last month’s newsletter, we mentioned that whilst all plans were focused on-site work physically starting during the week of August 3rd, there were two precursor activities outside of our control... by HydroCat | Jul 4, 2020 | Newsletters
With all the funding in place and the Hydro generation Scheme on course to be a reality (not just a dream!!), this is the first of a series of newsletters to keep you updated on key aspects of the project and progress towards generating the all-important Volts and...
by HydroCat | May 5, 2020 | Newsletters
At long last, after four years of planning, designing, calculating, learning, rucks of hard work, despair and euphoria, progressing one step at a time and sometimes backwards Congleton Hydro is set to become a reality. The Community Share Offer closed at midnight on...